Project Team
Michael Maltzan, FAIA | Principal
Brian Cavanaugh | Project Director
Steven Hsun Lee | Project Designer
Melanie Freeland | Job Captain
Yasushi Ishida
Yong Kim
Alex Morassut
Bill Mowat
Teh Park
Nick Sowers
Betty Tanaka | Marketing Director
Stacie Escario | Media Coordinator
Consultants
STRUCTURAL
John A Martin & Associates, Inc.
www.johnmartin.com T 213-483-6490
1212 S. Flower Street F 213-483-3084
Los Angeles, CA 90015
Kal Benuska, SE benuska@johnmartin.com
MEP/FP & SUSTAINABLE DESIGN
www.khalifeh.com
Khalifeh & Associates, Inc. T: 310-442-2288
12121 Wilshire Blvd., Suite 314 F: 310-442-2298
Los Angeles, CA 90025
Jack Khalifeh, Principal jack@khalifehassociates.com
CIVIL
Paller-Roberts Engineering, Inc.
www.pallerroberts.com T 310-641-1853
5701 Slauson Ave, Suite 208 F 310-641-1861
Culver City, CA 90230
Phil Roberts, President pr@pallerroberts.com
LANDSCAPE
LRM-Ltd Landscape Architecture
www.lrmltd.com T 310-839-6600
10950 Washington Boulevard, Suite 110 F 310-559-1310
Culver City, CA 90232
David Larkins, Managing Principal dlarkins@lrmltd.com
CONTRACTOR
www.westport.com
Westport Construction, Inc. T 626-447-2448
4333 E. Live Oak Ave. F 626-446-9221
Arcadia, CA 91066
John Bohling jbohling@westportconstructioninc.com
Project Notes
Client: Skid Row Housing Trust
643 South San Pedro Street, Los Angeles, California, 90014
near the intersection of South San Pedro and East 6th Street
43000 sq ft (3995 square meter)
87 efficiency units approximately 12 ft by 26 ft (3.65 m x 7.92 m)
$233 per sq ft (€1592 per square meter)
Total cost US $10 million ( €735240)
Principal structural system: concrete (ground floor), wood frame construction with steel bracing (five floors)
Principal materials: plaster, steel, glass, concrete